Back to Quotes
Draft · QT-2026-00009
Product / Service
Lead / CustomerDanville Kitchen remodel · Jay Agayev634 las barrancas dr, Danville, ca · Created May 27, 2026Open lead details and return to this quoteLine Item
Total
Protection materialsGroup: Kitchen Preparation & Demo
Site protection and dust control.
InternalCost $900Profit $315
$1,215
Demo laborQty: 56$123 eachGroup: Kitchen Preparation & Demo
Kitchen demolition and haul-away.
InternalCost $4,760Profit $2,142
$6,902
Electrical rough-in laborQty: 32$171 eachGroup: Electrical & Lighting
Lighting and outlet updates.
InternalCost $3,520Profit $1,936
$5,456
Cabinet installation laborGroup: Cabinetry
Cabinet installation and alignment.
InternalCost $12,800Profit $7,040
$19,840
Quartz countertop allowanceGroup: Countertops
Quartz countertop allowance.
InternalCost $8,500Profit $0
$8,500
Appliance install laborGroup: Appliance Installation
Standard appliance installation.
InternalCost $2,200Profit $990
$3,190
Extra recessed kitchen lightsOptional
Add extra recessed light locations beyond the standard lighting layout.
InternalCost $750Profit $450
$1,200
Quote Total
$45,103
Total profit $12,423